Oak Grove Avenue was repaved for its entire
length and was the only street repaved this year. The contract
was for $221,151.54. The Borough is in the process of reviewing
change orders in the approximate amount of $34,000.00 to replace
existing curb cuts.
This project was funded by a bond ordinance
in the amount of $325,000.00 with $235,000.00 in State of
NJ Department of Transportation Funds and the remaining $90,000.00
from Municipal Funds.
This project required that all curb cuts include
a detectable warning surface. This requirement applies to
the 39 existing curb cuts as well as any new cuts to be installed.
Also, any existing curb cut that does not meet current standards
must be replaced.
As with any repaving project the manholes
must be raised. In the case of Oak Grove Avenue, it was found
that approximately 12 of the castings were deteriorated and
in need of replacing.
As with any repaving, no sidewalks, curbs
or driveway aprons were replaced unless damaged by the construction.
Hasbrouck Heights does not have a street schedule
for 2007 yet, and they are working on the budget and capital
plan now.
They have, however, applied for grant funds
to repave Madison Avenue from the Boulevard to Terrace and
Division Avenue from The Boulevard to Terrace. Paving parts
of Central Avenue as part of the parking lot improvement is
also planned. ###